The City of Lethbridge has initiated a lawsuit amounting to $46.9 million concerning the guidance received during the funding and establishment of a $77-million trade and convention centre that was completed three years prior.
The Agri-food Hub and Trade Centre, which spans 24,900 square metres and is now recognized as the Lethbridge Trade and Convention Centre, was inaugurated in August 2023 on land owned by the city.
Shortly after the new facility was inaugurated, the city had to intervene and authorize emergency funding due to the construction costs exceeding the original budget by approximately $7 million, bringing the total to $70.6 million.
In 2024, a third-party assessment conducted by Deloitte Canada uncovered major problems with the project, revealing that the Lethbridge and District Exhibition (LDE) failed to communicate the need for more than $27 million in additional expenses until emergency funds were necessary.
Two years after the facility’s opening, the City of Lethbridge is pursuing legal action against the Calgary-based accounting firm MNP, as well as David Woodman, a former MNP staff member, and Mike Warkentin, the previous CEO of the Lethbridge and District Exhibition.

Former CEO of Lethbridge and District Exhibition Mike Warkentin presents to Lethbridge city council in August 2020. (City of Lethbridge)
The claims made in the city’s lawsuit have not yet been substantiated in a court of law. The three defendants have not filed any statements of defense thus far.
MNP has indicated to CBC News that it cannot comment since the case is currently in litigation. Attempts to reach Woodman through MNP were unsuccessful, as a spokesperson stated he had retired. A message left on his LinkedIn profile went unanswered, and CBC News was unable to contact Warkentin for his comments.
City influenced by two crucial presentations
In a claim submitted on June 26, the City of Lethbridge asserts that two significant presentations led to its support for the Agri-food Hub and Trade Centre as proposed by the LDE.
The municipality contends that Warkentin “knew or should have known” that he made “misrepresentations” that were “false,” “misleading,” and “negligently made in violation of a duty of care” during a presentation to a city committee in June 2019.
During this presentation, the city alleges that Warkentin claimed the financial models for the project conservatively predicted “a positive cash flow outlook” for the following 24 years, indicating its sustainability.
More than a year later, on August 10, 2020, Warkentin informed the council that the LDE would not require additional city funding to operate the new facility, as stated in the City of Lethbridge’s legal claim.
Woodman from MNP also spoke at the 2020 council meeting (by phone due to the COVID-19 pandemic). According to the city’s lawsuit, Woodman informed the council that a “very significant third-party cost analysis” had been conducted that year.
He also claimed that LDE had done a “very good job” in identifying and mitigating risks, as per the city’s lawsuit.
“The involvement of Woodman as a representative of MNP, along with the August 2020 Woodman/MNP Misrepresentations, was meant to lend professional credibility to the LDE and the business justification presented to the City, which the Defendants understood at all relevant times,” alleges the City of Lethbridge.
However, the city claims that Woodman “knew or should have known” that his involvement and statements during the August 2020 meeting were “misleading, negligent, and misrepresentative of MNP.”
“Had it not been for the Defendants’ Misrepresentations and Omissions, the City would not have approved the LDE Requests nor provided the associated benefits,” states the City of Lethbridge’s claim.
Council approves LDE requests
On August 24, 2020, city council sanctioned a 30-year loan of up to $17.8 million, $25 million in funding, a 50-year site lease with an option to renew for another 50 years, along with forgiving a 2010 loan balance of $3.8 million in exchange for approximately 63 hectares of LDE-owned land.
The project also received financial support from the Alberta government ($27.8 million), the federal government ($3.5 million), and Lethbridge County ($2 million).
City pursuing nearly $47 million
The city is seeking damages of $46.9 million from the defendants, which includes $17.8 million for “losses and damages related” to the 30-year loan and the $25 million in city funding for the Agri-food Hub and Trade Centre.
Additionally, the city states that it continues to operate the LDE and cover its costs, estimated at approximately $4.1 million as per the lawsuit.
In 2025, the LDE was divided into two organizations. Excite Lethbridge is responsible for promoting and booking events at the Lethbridge Trade and Convention Centre, while the Lethbridge and District Agricultural Society focuses on agricultural promotion in the area.

Lethbridge city hall pictured on May 12, 2026. (Ose Irete/CBC)
In a press release dated October 30, the City of Lethbridge stated that the lawsuit was initiated “to safeguard the financial interests of Lethbridge residents and the municipality.”
As the case is now in court, the city has stated that it will refrain from making any further comments.